It was revealed at the Committee on Public Accounts (COPA) that 72 development projects initiated between 2018 and 2021 by the Ministry of Education, Higher Education and Vocational Education have been stalled halfway. These details were presented when the committee met in Parliament on the 19th under the chairmanship of Member of Parliament Kabir Hashim.

It was disclosed that Rs 1,664 million had been spent on these 72 stalled projects. Of these, 35 projects have been completed by now, while work on 13 is currently ongoing. However, officials stated that 20 projects have been halted due to contractual issues, and another 4 projects have been suspended.

Key Highlights

  • Rs 1,664 million spent on 72 projects initiated between 2018 and 2021.
  • 20 projects halted due to contractual issues, while 4 others have been suspended.
  • Supplier files court cases after substandard consignment of computers was rejected.

National schools project and computer litigation

In 2019, nearly Rs 1,600 million was allocated for a programme to establish three national schools per Divisional Secretariat division. However, as the programme was halted due to policy decisions, the committee directed that a report detailing the funds allocated to each school and the work completed be submitted.

Meanwhile, it was also revealed that a consignment of computers ordered by the Ministry was not accepted as it did not meet the technical specifications. The supplier has filed two court cases against the Ministry as payments were withheld.

NEMIS system and emerging bottlenecks

It was mentioned that priority has been given to entering teacher information and student evaluation data via the National Education Management Information System (NEMIS), and teacher transfers in several provinces are already being handled through this system. Plans are in place to expand this system across all provinces and national schools.

The Department of Communication of Parliament stated that delays in estimates, shortages of technical officers, and tender-related issues have posed obstacles to the utilisation of capital provisions, and the committee instructed that immediate steps be taken to resolve delays related to audit queries.